The Deputy Minister of Digital Economy, Eranga Weeraratne, says that damaged telephone and internet networks should be fully restored by tomorrow (04 December).
The Ministry of Digital Economy, the Telecommunications Regulatory Commission, and all providers are working intensely to bring services back online.
Restoration Progress
- Fibre Connections: All provincial fibre connections are now operational. Damaged routes are being managed using alternative fibre paths.
- Transmission Towers: Over 4,000 main transmission towers failed due to power cuts and fibre breaks. Approximately 2,800 towers have been fixed so far.
- Power Issues: The remaining 949 inactive towers are mainly down due to power outages. Service providers are working with authorities to restore power quickly. The Tri-Forces are giving maximum support to reach towers and provide necessary power.
Affected Areas
While over 80% of disruptions are now resolved, problems remain mainly in the Nuwara Eliya, Badulla, Puttalam, and Vavuniya districts. Nuwara Eliya and Kandy are the most affected.
- Nuwara Eliya and Puttalam: The Ministry expects over 75% connectivity to be restored by tomorrow morning.
- Kandy: Restoration is aimed to increase from the current 65% to around 70%.
The Minister stressed that communication is vital for public safety and keeping in touch with family, expressing confidence that full restoration will be achieved by tomorrow.
Last modified: December 3, 2025